Project Updates Part II: The Black Hart of St. Paul Patio

Swift progress continues over at the Black Hart of St. Paul patio project. The space is taking the form of its final product which will transform a strip of University Ave that previously sat vacant. Plus, St. Paul will gain another beautiful beer garden.

Some updates from the past week:

  • The perimeter fence is 95% complete

  • All 6x6 vertical posts are in

    • the Simpson Moment post bases live up to their advertised capabilities

    • the posts are 11’ tall and don’t move a bit

  • Concrete saw subcontractors have cut the opening for the door

Concrete saw subcontractor cutting to the door to the patio